Gulf Shores Pedestrian Bridge Project Reaches Key Milestones

R. Ken Cooper • January 24, 2026

Project Passes 47 Percent Completion Mark As Work Advances

Gulf Shores Pedestrian Bridge Project Reaches Key Milestones

Gulf Shores, Ala. — (OBA) — We see some people asking why the pedestrian bridge is being built. The pedestrian bridge is needed to eliminate the pedestrian lane on the Hwy 59 Bridge. Once the pedestrian bridge is completed, it will allow a 3rd traffic lane on the Holmes Bridge (Hwy 59).


Construction on the City of Gulf Shores’ pedestrian bridge is progressing as planned, with crews reaching several visible milestones. City officials report steady progress on roadway work, bridge construction, and elevator towers. The project continues to move forward without significant delays. Officials say work remains on schedule according to the contract.


As of this update, the pedestrian bridge project is 47.4 percent complete under the contract schedule. Subcontractors are scheduled to return to active roadway construction on Monday, January 26. Their work will focus on revisions to the ALT 1 typical section and continued curb and gutter construction along ALT 2.


ALT 1 and ALT 2 refer to the two new approach roadway segments that will carry traffic to and from the pedestrian bridge and elevator towers on each side of the Intracoastal Waterway. They include the reconfigured travel lanes, curb and gutter, and sidewalk areas that tie the bridge landings back into the existing street network, and are being built in phases so local access can be maintained while construction continues.


Recent progress includes significant developments on both sides of the Intracoastal Waterway. On the north side, all 15 bridge pilings have been saw-cut. Crews have started removing material to reach the necessary elevation for pile cap installation.


On the south side of the bridge, contractors are preparing for the next phase of the structure. The first vertical section of the South Bridge Bent Columns is expected to be poured within the next two weeks. This step marks another key transition in the bridge’s framework.


Work on the elevator towers also reached an important milestone earlier this week. On Wednesday, January 21, crews completed the final vertical section pour for the South Elevator Tower. City officials described the pour as a major achievement for the project.


Pile driving work has also been completed on the North Elevator Tower. Contractors successfully installed two piles to repair Pile 11. With that work finished, all pile driving activities for the elevator towers are now complete.


Traffic restrictions remain in place as construction continues. East 2nd Street between 23rd Avenue and 24th Avenue is still limited to local traffic only. The restriction is expected to remain through mid-February while pavement, curb, gutter, and sidewalk work is finalized.


Traffic north of the Intracoastal Waterway is also limited to local access during ongoing ALT 2 construction. City officials noted that no utility relocation work was performed during the most recent reporting period.


Erosion control measures continue to be monitored and maintained throughout the site. Contractors are repairing best management practices as needed. A pump system remains in operation on the north side of the waterway to manage the pile pit area.


The pump system will stay in place until all piles are cut off and pile caps are completed. These measures are intended to protect surrounding areas while construction activities continue.


Looking ahead, pile driving crews are expected to finish cutting elevator piles on the north side soon. The contractor is anticipated to demobilize by early February. Work will also continue on the South Elevator Tower’s internal slabs and ALT 1 roadway revisions.


Share this article w/ Friends...

54th Annual Art In The Park Returns To Downtown Foley
By OBA Staff April 28, 2026
Foley, Ala. — (OBA) — The Foley Art Center will host the 54th Annual Art in the Park in Heritage Park on Mother’s Day Weekend in downtown Foley. The event is held each year at the intersection of Highways 59 and 98. Planners say the festival will feature more than 80 artists. The event is free and open to the public.
Three Makos Teams Ready for Postseason Play This Week
By John Mullen April 28, 2026
Orange Beach, Ala. – (OBA) – It’ll be a busy week in post-season play for at least three Orange Beach Makos spring sports teams. Two teams – baseball and girls' soccer – will play state tournament games, with baseball at home and girls' soccer on the road. The Lady Makos softball powerhouse will be the host team for...
Residential Developments Proposed Near Hospital, Sportsplex, and Oyster Bay
By John Mullen April 28, 2026
Gulf Shores, Ala. – (OBA) – A short meeting agenda for the Gulf Shores Planning Commission is long on requests for 256 new residences in three subdivisions planned in the city. Expansion areas include one for townhomes across State Route 59 from the Baldwin Regional Medical Center’s freestanding emergency department.
South Chicago Street in Foley has reopened after being closed for several months
for improvements.
By Guy Busby April 27, 2026
Foley, Ala. — (OBA) — South Chicago Street in Foley has reopened after several months of closure for improvements. The project added new visual features and pedestrian upgrades along the roadway. City officials said the changes are part of a broader effort to improve access to downtown. The street now includes...
PicOrange Beach Pickleball Complex Grand Opening Is Set for Next Week
By OBA Staff April 27, 2026
Orange Beach, Ala. — (OBA) — The City of Orange Beach is getting ready to open a brand-new pickleball complex, and the city is inviting everyone to come celebrate. The Orange Beach Parks & Recreation Department announced the grand opening and ribbon-cutting ceremony for the new Orange Beach Pickleball Complex.
NCAA Championship Volleyball - Stock Photo
By OBA Staff April 27, 2026
Gulf Shores, Ala. — (OBA) — Gulf Shores is preparing to host a major collegiate sporting event as top teams from across the country arrive for the national championship. The competition will feature 16 of the nation’s leading beach volleyball teams, with matches held on the city’s public beaches. Officials expect...
=Your Weekly Guide to What’s Happening at the Beach: Adventure, Elegance & Coastal Fun
By Jessica A. Taylor April 27, 2026
Orange Beach, Ala. — (OBA) — Never fear–your weekly guide to what’s going on and what to do at the beach is here, and you're in for a good one. This lineup of coastal events brings a little bit of everything–from treetop thrills and luxury cruises to community celebrations and sky-high spectacles that truly shine.
Orange Beach Powerboat Week Returns to Orange Beach in May
By OBA Staff April 26, 2026
Orange Beach, Ala. — (OBA) — Powerboat teams from across the southern United States will be gathering in Orange Beach for the 7th Annual Orange Beach Powerboat Week. The multi-day event will be held at The Wharf, the central hub for all activities. Organizers say the event draws participants from Texas to the Atlantic
Gulf Shores City Schools Launches Adult Culinary Class Series
By OBA Staff April 26, 2026
Gulf Shores, Ala. — (OBA) — Gulf Shores City Schools is launching a new adult culinary class series called The Art of Culinary. The series is designed to celebrate food, learning, and community. Organizers said the classes will be hands-on and led by Chef Jon Kastner and other local experts. Each class will focus on a
Baldwin County Voters Urged to Plan for May Primary Election
By OBA Staff April 26, 2026
Orange Beach, Ala. — (OBA) — Baldwin County voters have an important date approaching, and officials want them ready. The May 19 primary election is coming up fast. A little planning can go a long way toward a smooth voting experience. Taking a few simple steps now can make Election Day much easier.
Show More